Ground broken.Walls next.

The schedule as it actually moves. Seven phases, two years, one hole in the ground that is slowly becoming a basement.

Everything here is updated as the site changes. Percentages are the builder's estimate of work in place, not money spent.

Phase 2 of 7 · Site & foundation

Excavation, footings and basement walls.

Overall

Average of 7 phases · weighted equally

Weeks since start
46
Counted from Nov 2025
Phases complete
1of 7
Design & permits
Next milestone
Nov 2026
Site & foundation finished
Timeline

Seven phases,two winters.

  1. 01Design & permits

    Nov 2025 — Aug 2026

    100%

    Drawings sealed and permit issued.

  2. 02Site & foundation

    Sep 2026 — Nov 2026

    35%

    Excavation, footings and basement walls.

  3. 03Framing & roof

    Nov 2026 — Feb 2027

    0%

    Floors, walls, trusses and sheathing.

  4. 04Windows & envelope

    Feb 2027 — Apr 2027

    0%

    Windows, doors, weather barrier, cladding.

  5. 05Mechanical & electrical

    Mar 2027 — Jun 2027

    0%

    Rough-ins, insulation, drywall.

  6. 06Finishes

    Jun 2027 — Oct 2027

    0%

    Cabinetry, tile, floors, paint.

  7. 07Handover

    Oct 2027 — Nov 2027

    0%

    Punch list, landscaping, move in.

Planned vs actual

On the line,so far.

Reading

18%

Work in place at Sep 2026, 1 pt ahead.

  • Actual
  • Planned
  • Planned, ahead

Percent of build complete, by month · dashed is the plan ahead of today

Area under roof

Where thesquare feet go.

6,558 sq ft under roof · 3,527 conditioned

Envelope

Wrappedwarm.

  • WallsR-21
  • RoofR-49
  • FloorsR-30
  • BasementR-13
  • Slab edgeR-10

Nominal R-values, IRC 2021 · IECC 2018. Rings scaled to the roof.

A note

Figures are indicative and updated as the build moves.