04 — Build
Ground broken.Walls next.
The schedule as it actually moves. Seven phases, two years, one hole in the ground that is slowly becoming a basement.
Everything here is updated as the site changes. Percentages are the builder's estimate of work in place, not money spent.
Phase 2 of 7 · Site & foundation
Excavation, footings and basement walls.
Overall
Average of 7 phases · weighted equally
- Weeks since start
- 46
- Counted from Nov 2025
- Phases complete
- 1of 7
- Design & permits
- Next milestone
- Nov 2026
- Site & foundation finished
Seven phases,two winters.
- 01Design & permits
Nov 2025 — Aug 2026
100%Drawings sealed and permit issued.
- 02Site & foundation
Sep 2026 — Nov 2026
35%Excavation, footings and basement walls.
- 03Framing & roof
Nov 2026 — Feb 2027
0%Floors, walls, trusses and sheathing.
- 04Windows & envelope
Feb 2027 — Apr 2027
0%Windows, doors, weather barrier, cladding.
- 05Mechanical & electrical
Mar 2027 — Jun 2027
0%Rough-ins, insulation, drywall.
- 06Finishes
Jun 2027 — Oct 2027
0%Cabinetry, tile, floors, paint.
- 07Handover
Oct 2027 — Nov 2027
0%Punch list, landscaping, move in.
On the line,so far.
Reading
18%
Work in place at Sep 2026, 1 pt ahead.
- Actual
- Planned
- Planned, ahead
Percent of build complete, by month · dashed is the plan ahead of today
Area under roof
Where thesquare feet go.
6,558 sq ft under roof · 3,527 conditioned
Envelope
Wrappedwarm.
- WallsR-21
- RoofR-49
- FloorsR-30
- BasementR-13
- Slab edgeR-10
Nominal R-values, IRC 2021 · IECC 2018. Rings scaled to the roof.
A note
Figures are indicative and updated as the build moves.
Read the journal